C722 Project Management Practice Questions - Set 2 - Part 1
Test your knowledge of Project Management concepts with these practice questions. Each question includes detailed explanations to help you understand the correct answers.
Question 1: What is the most common relationship between tasks in a project schedule, where the successor activity cannot begin until the predecessor activity has been completed?
Question 2: In project cost management, what is the difference between the Earned Value (EV) and the Actual Cost (AC) used to determine?
Question 3: Which phase includes identifying and defining project requirements, as well as documenting scope, stakeholders, and high-level risks?
Question 4: What type of organizational structure is characterized by having clear lines of authority within departments and is commonly used in government agencies?
Question 5: Which project management method organizes tasks into a linear sequence where each phase must be completed before moving to the next?
Question 6: What cost estimation method leverages prior project data to calculate costs based on unit costs or rates?
Question 7: In Agile project management, what document is created to capture all required features and functionality as requested by the customer?
Question 8: What technique is used when compressing a schedule by assigning additional resources to critical tasks?
Question 9: Which term refers to adjusting tasks or activities to reduce peaks and valleys in resource allocation, helping maintain consistent resource use?
Question 10: In a project, what kind of costs are directly related to completing the work and can be clearly attributed to specific tasks?
Question 11: Which type of cost estimation starts with the highest level and progressively refines costs as more information is available?
Question 12: Which project phase involves reassessing project objectives and reassigning resources for future use once deliverables are accepted?
Question 13: What tool provides a visual representation of resource requirements over time and is helpful for balancing resource allocation?
Question 14: What is an “Opportunity” in risk management terms?
Question 15: Which type of task dependency requires a task to be delayed before its successor can begin?
Question 16: What estimating technique calculates an average by weighting the most likely estimate more heavily than optimistic and pessimistic estimates?
Question 17: Which document establishes how stakeholders will be identified, their level of interest, and communication needs throughout the project lifecycle?
Question 18: What analysis evaluates whether the project’s budget expectations align with actual spending, using Earned Value (EV) and Actual Cost (AC) data?
Question 19: Which estimating technique would be appropriate when activity durations are highly predictable?
Question 20: What is the term for the calculated difference between the finish date of the last activity on the critical path and the project’s scheduled completion date?
Need Guaranteed Results?
Don't want to study? Our exam support service guarantees you'll pass your OA on the first attempt. Pay only after you pass!
Get Exam Support